Substantial Judgment for Contractor
March 2016
The firm was retained to assist a contractor sued arising from a construction project at the Huntsville, Alabama airport. The client counterclaimed. On March 3, 2016, the Court entered a partial summary judgment in favor of the client for $415,843.30 plus 8% interest from September 15, 2012, with a final hearing set to determine the client’s recovery of attorney’s fees and additional delay costs of $134,000. The Court dismissed plaintiff’s complaint with prejudice. Pending the final hearing to assess further damages and attorney’s fees, the case was settled.

G. Rick Hall
J. Mike Tanner
Douglas B. Hargett